Within Teamwork Projects, risks are possible events that can have an impact on the success of your project.

You can record and track risks in each of your projects, and note a mitigation/response plan so your team knows what to do when a risk develops into an issue.



For each risk, you can specify:

  • Probability of risk source happening
    • 1 - 3 (low impact)
    • 4 - 6 (medium impact)
    • 7 - 9 (high impact)
  • Impact on project if risk source happens
    • 1 - 3 (low impact)
    • 4 - 6 (medium impact)
    • 7 - 9 (high impact)
  • Status
    • Open
    • Pending
    • Closed
  • Impact Areas
    • Cost
    • Schedule
    • Performance
Once a risk has been added, you will see the risk result has been calculated based on.

  • Risk result = (probability) x (impact)

For more information on risks see: Adding a risk