Within Teamwork Projects, you can use the projects chart for a Gantt-style view of your projects, highlighting any milestones on the project timeline.

To access the projects chart, go to the Projects area at the top of your site, and select the Chart tab:



Note: Only projects with start and end dates will show on the chart. 

To show the projects chart, add start and end dates to at least 2 projects and ensure the filter to the right includes the relevant timeframe

The bar for each project will be coloured based on the status of the project:

  • Red : This means that the project end date has been reached but there are uncompleted items in the project. The project is considered late.
  • Green: The project has been marked as complete.
  • Blue: The end date has not been reached and the project is considered 'current'.
If you hover over the project bar, you will see more project details and an option to edit the start and end dates directly:


The markers for milestones are also colour coded based on whether they are complete (green), late (red) or upcoming (orange).

If you hover over each milestone, you will see more details and a quick view option (if there's more than one milestone due on the same date, you'll see them all listed here):



Using quick view, you can view and edit the milestone directly without leaving the projects chart screen.

In the project list on the left, you will see the category colour to the far left, and you can access the project options menu to make changes without leaving the projects chart:


You can also use the arrows to the right of the project name to automatically scroll and zoom to that project on the chart.

Note: Collaborators can view the projects chart but do not have edit permissions.

For more information, see: Gantt Chart